Tuesday, 1 November 2011

Building Permit Stage

We'd spent in excess of 12 months designing our new home using various software, then unable to take it any further, we appointed a Draftsperson and other specialists to make it real and fine tune it all.

On 24th November we lodged our Plans to Council for Permit approval.

These included: 
  1. Relevant Plans of Subdivision, Transfer of Land, etc.
  2. Scaled Site Drawings showing the Dwelling, Shed, Septic Treatment Plant location
  3. Building Practitioners Board - Certificate of Consent to Owner Build; 
  4. Shed and Septic layout; 
  5. Soil Test Report;  
  6. 5 Star Energy Rating; 
  7. Legal Point of Discharge
  8. Structural & Slab Engineering Designs; 
  9. Elevation Plan
  10. Detailed Floor Plan
  11. Shed Layout;
  12. Electrical Layout.

The whole process took approximately 6 weeks, but bearing in mind that the Xmas Season was in the middle of it all. 

Final approval and Building Permits were signed off on 16th January 2012.

Time to make a start ...... The Shed First!!


Our Professionally Created Sign

Cross-over with Crushed Rock

At the rear of our land, what remains of the previous slashing and grading is a Grass & Rock Hill which will eventually decompose and reduce in height

Taking it all in at this very early stage