Monday, 5 August 2013

Framing complete and ready for Council Framing Inspection

Carpenters completed all of the framing (walls, truss, roof battens, bracing, etc.) Now ready for Framing Inspection on Wednesday, 7th.

Finishing off, final few braces 
Portico Roof trusses in place

Alfresco
West facing rear of house 

Rear - North South 
Looking from the south of the front

Looking up into the puzzle of roof trusses now installed into the Portico 

Looking from the Garage through into the Laundry 
Looking out into the Alfresco from the Family Room 

Looking into the Alfresco from the Kitchen 
Looking from the Kitchen towards the Foyer and Entrance
Son and Daughter discussing the build
The Foyer from the Centre of the Family Room & Dining Room
Our Carpenter Mick finishing off 
This wall will house the BBQ area cabinets with a block return wall to and around the Steel Galvanised Post
This post had to be adjusted and with the help of our Welder Neighbour was corrected. When the concretors were laying the slab on ground, they added fall to the alfresco area so as to avoid any water build up or pooling. When the steel posts were ordered, we forgot to make the adjustment. All good now though.