Day 3: Monday - Slab Preparation
Another very Cold morning. Contractors had a day off yesterday, Sunday, a well earned rest, and are back to work today.
Slab starting to take more shape now with Formwork complete, Reinforced Steel and Chairs being placed into Position.
Again, no rain is forecast, even though it looks a little overcast at times.
Ready for inspection tomorrow.