Tuesday, 21 February 2012

The Man Shed Slab continues .... Day 2

Today will be final setup of slab formwork, sand, moisture barrier sheets and most importantly the reinforced steel in preparation for the pour tomorrow. In addition to the Shed Slab the Concrete Contractor has set up for the pouring of a 5 metre by 5 metre, 4 inch deep slab base for the first of our three Polymaster Water Tanks on the property. This one will be a massive 31,700 Litres. That's a whopping 31 Tonne of weight when full and will be used purely for gardening and maintenance.

Moisture Barrier Sheets being laid

Formwork in place and reinforced steel set up. Horizontal Orange pipe is conduit for our Electricity.

... and as a bonus, our Fencing Contractor has turned up to mark out the position of our front boundary fencing. Looking South from our Crossover.

Looking North from our Crossover


Shed Permit documentation placed on our Sign
All ready for the big pour tomorrow ....