Thursday, 19 April 2012

More Walls up on the Shed and the Arrival of our Water Tank

Two days later, the Shed is coming along nicely and we have the delivery of our Water Tank. This is placed into position and as you can see there's not much room left around the perimeter of our 5 metre x 5 metre square concrete pad. The external wall colour of our Shed is ColourBond "Ironstone" and therefore we thought it best to match the Water Tank to the Shed colours.


More walls up now 
Our 31,700 litre Water Tank in position.
It took the Semi-Driver, Scott and the Shed Installer to manoeuvre into position.
The dry weight of the tank is over 500 kg.
Perfect Match, we're very happy



Tuesday, 17 April 2012

An American Barn Man Shed coming to life

Shed Installer Contractor has been on site for a few days now. The weather forecast will be taking a turn for the worse and what has been a lovely clean slab is destined to become black with mud from all the rain. Nothing that a little scrubbing and high pressure cleaning won't fix once it's totally complete.


Our American Barn finally taking shape with majority of frame up and the north wall standing






Electrical Cable ready for Inspection by Electrical Inspector. He will install the new Meter Box.
 Pegs are the set-out for our new Home

More homes are being built all around us. We have five neighbours all up but we're quite a distance from each other.

Friday, 13 April 2012

3 Phase Electricity Connection

Today our Electrical Contractor excavated a trench approximately 40 metres diagonally from the front boundary to run cable within conduit for the connection of our requested 3 Phase Power approved/granted by Powercor.

Excavation of a trench where the main Smart Meter Box will be located on the South side of our new home.
Two young apprentices learning how to join conduit

That's alot of conduit


That's a big hole ..... 
A largish boulder dug out from the trench ... and yes, another landscaping rock!

Preparing to dig the start of the trench from the Electricity Pit which is shared by us and our adjoining neighbour. Note that our new neighbours loved our fencing so much that they appointed the same Contractor to build them one too..... Awesome!


















Such precision ..... so that's how it's done
Our Shed Contractor is on site preparing for the erection of our new Shed.


Monday, 19 March 2012

Stained our Front Fence

After much research and talking with experts, it was established that regardless of what we used (oil based vs water based stain) no one manufacturer would provide a guarantee that it would last X amount of time before re-applying.


Therefore we chose Haymes Dexpress in the Jarrah colour. This is a product that we have personally used on the ceiling of our current outdoor alfresco area and over the last 12 years, we have always preferred to use Haymes products.


Two coats and we are very pleased with the final result.

We totally love the colour and we've achieved the overall look that we imagined