Friday 21 September 2012

Tiling! ..... and it continues

Tiling continuing to go up the Bathroom Wall
Tile Height sitting at 2100mm from Floor level in and around Shower Base
Tiling wraps around to window height and behind where our Toilet Suite will be positioned
What's left is the Window ledge and behind the Vanity Unit at approx. 1240mm height

Saturday 1 September 2012

Shower Base tiling a little tricky!

Floor Tiling continues in the Bathroom with the Shower base tiling proving to be both time consuming and a little tricky. Now we understand why Builders and Tilers use the small mosaic sheets of tiles for shower floors. They allow for more manoeuvrability. We however have preferred to use the same tile throughout. Persistence has paid off as the most important thing is to get the tile cuts and levels correct so that you have fall of water directly to the drain. A job well done. Will complete the walls in the bathroom and then grout.

Looking good!
Cutting tiles
What man-shed would be complete without some organised storage for tools and the like?

Have installed a timber board which after a couple of coats of black blackboard paint will do nicely for hanging storage systems and loose tools and gadgets. 



Had a bit of a clean up and burn-off of boxes. They come thick and fast with every new item or fitting. Kids first had a bit of a play in one of the huge boxes before the burn-off though.



Who doesn't enjoy watching a fire?


Keeping watch with Bucket of Water ready!


..... and Spring is finally here and what a beautiful sunny day.

Tuesday 28 August 2012

Planning the Shower Base Tiling

Planning the shower base. Laying out tiles to see what will work best.
 

Final few cut outs for tiles required around the plumbing. Now Kitchen tiles ready to grout.


Monday 20 August 2012

Base Coat on Walls ....

Messing around on the Ride-on Mower obviously with blades disengaged!
Vrooooooom!!
Wheeeeeeeeeeeeeeee!
Just 6 more years before I can drive!!
Base Coat Painted on Walls
We all know what a coat of paint will do to brighten things up!



We've decided to try the Dulux "Antique White USA" that everyone brags about. If we like it in the Shed, then we may use it in the new House. 
We're also leaning towards "Whisper White". 
Will upload photos when we've painted two coats in a few weeks. 


Friday 10 August 2012

Let there be Light! ..... Finally Electricals connected.

Today our Electrician installed Fluro Lights, Powerpoints, Hot Water Service, Hotplates and external Sensor Lights. Lighting is all low voltage. 

Cooking Dinner (Burgers) as the Hot Plates are connected
Lights


Tiling Floor in Bathroom has commenced


A couple of mm has to be shaved off the bottom of the Bathroom Door to allow opening and closing

Switchboard mounted and Light Switches
Hot Water Unit in position and connected. Now the Plumber needs to finish off his water connection.
Tiles in Kitchen now ready for Grouting
Taking it all in

A Shed tidy up and reorganisation creates a bigger space to work in and walk around



Love the Kitchen

Wednesday 8 August 2012

An eventful day in the Man-Shed!

Quite an eventful day today with the following projects:
  1. Waterproofing completed in Bathroom
  2. Cornice on Shed North Wall installed
  3. Plaster received a final Skim Coat
  4. Holes in Door Architraves and Skirting Punched and Puttied
  5. Commenced Tiling in Kitchen
Ardex SuperFlex WPM 001 - Waterproofing Membrane - Brushed and Rolled
Now Dry First Coat
Completed Second Coat. Quite a lovely shade of Blue







The last of cornice installed on Northern Shed Wall
Let the Tiling begin .....!
Missing tiles need to be cut with hole saw attachment

An absolute Perfect Match in Tile & Kitchen colours 

Will continue with tiling tomorrow 
Plaster walls skimmed, then need sanding prior to painting