- Waterproofing completed in Bathroom
- Cornice on Shed North Wall installed
- Plaster received a final Skim Coat
- Holes in Door Architraves and Skirting Punched and Puttied
- Commenced Tiling in Kitchen
![]() |
| Ardex SuperFlex WPM 001 - Waterproofing Membrane - Brushed and Rolled |
![]() |
| Now Dry First Coat |
![]() |
| Completed Second Coat. Quite a lovely shade of Blue |
![]() |
![]() |
| The last of cornice installed on Northern Shed Wall |
![]() |
| Let the Tiling begin .....! |
| Missing tiles need to be cut with hole saw attachment |
| An absolute Perfect Match in Tile & Kitchen colours |
| Will continue with tiling tomorrow |
| Plaster walls skimmed, then need sanding prior to painting |